I've had my new mill since the spring.  I have finally found time to get started on my mill shed.  It is going to be a simple 20x48 pole barn with poles set 12ft on center.  I left out the center pole on one side of the barn and will clear span that 24ft section with a piece of steel.  That's where the mill will sit.  Don't want a pole in the way of loading logs on the mill.  I plan on building my trusses when I take a week off my regular 9 to 5 job.  Hope to post more pictures as I progress. 

  

  

  

 

Those last couple pictures are of me setting a piece of 8x8 - 1/2 inch angle that came from an old power line tower. 
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

tmbrcruiser

Congratulations on the building!
Once you get sap in your veins, you will always have sawdust in your pockets.

Magicman

That will be a fine sawmill shed.   8)
Knothole Sawmill, LLC     '98 Wood-Mizer LT40SuperHydraulic   WM Million BF Club Member   WM Pro Sawyer Network

It's Weird being the Same Age as Old People

Never allow your "need" to make money to exceed your "desire" to provide quality service.....The Magicman

sandsawmill14

hudson 228, lucky knuckleboom,stihl 038 064 441 magnum

ayerwood

Very nice.  I will be following you as I need to build one sooner than later too.  Congrats!!!

fishfighter


WDH

Looks like a shady spot, too.
Woodmizer LT40HDD35, John Deere 2155, Kubota M5-111, Kubota L2501, Nyle L53 Dehumidification Kiln, and a passion for all things with leafs, twigs, and bark.  hamsleyhardwood.com

deepsouth.us

This will be a fine shed indeed.
How tall to your top plate? And how deep did you set your poles? Is that an old industrial massey?
Timberking 2000

Ga Mtn Man

Nice spot for a shed and that angle iron was a great find.
"If the women don't find you handsome they should at least find you handy." - Red Green


2012 LT40HDG29 with "Superized" hydraulics,  2 LogRite cant hooks, home-built log arch.

btulloh

Nice looking shed.  I will be following your progress.  Great find on the steel.  Maybe I'll be lucky enough to find a piece of steel like that to build a shed around.
HM126

WV Sawmiller

NC,

    Your design looks very much like my lumber storage shed below. I used locust poles cut off my place and partially squared on the side where nailed. I left openings in the front over 18' in case I ever wanted to load 16' lumber with a future forklift/tractor. I got used tin/roofing off a guy tearing down a barn and have enough left to add another 20' extension which I will do one of these day (after deer season and such). That is all the space I have left on the lot there for expansion. My whole shed is costing me under $400 especially since I sold some left over tin/roofing a month or so back.

   Good looking work. Be careful. Too many falls reported by members recently while working on such projects. Don't add your name to that list.


 
Howard Green
WM LT35HDG25(2015) , 2011 4WD F150 Ford Lariat PU, Kawasaki 650 ATV, Stihl 440 Chainsaw, homemade logging arch (w/custom built rear log dolly), JD 750 w/4' wide Bushhog brand FEL

Dad always said "You can shear a sheep a bunch of times but you can only skin him once

ncsawyer

Quote from: deepsouth.us on September 21, 2015, 07:58:07 AM
This will be a fine shed indeed.
How tall to your top plate? And how deep did you set your poles? Is that an old industrial massey?

The top of the plate is 10.5 feet.  I dug my holes 4 ft and put 6 inches of concrete in the bottom of each hole to set my poles on.  This will hopefully keep them from settling.  My plates are 10 inches, it's just under 10 feet at the bottom of the plate. And the tractor is an industrial Ford 445.  I've had it 3 years and it's definitely paid for itself.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

beenthere

How much of the steel angle header is sitting on the posts at the ends? Doesn't look like much from the pics.
I'd worry about bumping a post with log or loader enough to knock it off the post and the roof fall.. maybe that is an unfounded worry here.
south central Wisconsin
It may be that my sole purpose in life is simply to serve as a warning to others

ncsawyer

WV,

That's a nice lumber shed.  I wish we had locust around here.  I had to buy my poles, so I'll have more invested in mine than yours, but it will certainly be  cheaper than hiring somebody to build it.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

Quote from: beenthere on September 21, 2015, 11:04:32 PM
How much of the steel angle header is sitting on the posts at the ends? Doesn't look like much from the pics.
I'd worry about bumping a post with log or loader enough to knock it off the post and the roof fall.. maybe that is an unfounded worry here.

The posts are 6x6, so it's sitting on 3 inch of post on either side.  I bolted it to the posts with 5/8 inch galvanized bolts.  Also there will be a 10 inch plate bolted to the steel that will tie the piece of steel to the post it is sitting on and run back to the end posts to tie everything together.   I'll post some more pictures in a couple days so you can see what I mean.  Hopefully I won't bump a post hard enough too test my design.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

I've made some more progress on the new mill shelter.  It is to the point where the trusses are ready to be set.  It supposed to rain for the next couple days and some next week.  As soon as it quits raining I will be able to saw the lumber for the trusses, build them, and get them set.  I also have a guy coming to weld brackets on top of the piece of angle to bolt my trusses to.   

  

 

These pictures show where I have finished putting the plate and braces all the way around.  I bolted a 2x10 plate to the angle iron as well.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

Buddyw

Looking good.
Always nice to have a new building.

ncsawyer

After two solid weeks of rain, it has finally dried out enough to get back to work on the building.  I hope to have the roof on it in a couple of days.   

 
This is a picture of some of the trusses I made before that were put up.  They span 20 feet and have a 2 foot overhang on each side.


  

 
Those are two pictures of my truss setting apparatus.  Which is just an old piece of gas pipeline pipe slid over one of my forks on the tractor.


 

That's just a good picture of me in action with the mill in the background.  My wife took that one.  She's makes a better photographer than carpenter.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

CaseyK

NC sawyer, project is looking great, thanks for sharing your build with us. Be safe.

Casey K
Home built automated twin blade

WDH

Good idea on the boom lift.
Woodmizer LT40HDD35, John Deere 2155, Kubota M5-111, Kubota L2501, Nyle L53 Dehumidification Kiln, and a passion for all things with leafs, twigs, and bark.  hamsleyhardwood.com

thecfarm

Model 6020-20hp Manual Thomas bandsaw,TC40A 4wd 40 hp New Holland tractor, 450 Norse Winch, Heatmor 400 OWB,YCC 1978-79

Sixacresand

"Sometimes you can make more hay with less equipment if you just use your head."  Tom, Forestry Forum.  Tenth year with a LT40 Woodmizer,

Magicman

You are moving right along and looking good.   8)
Knothole Sawmill, LLC     '98 Wood-Mizer LT40SuperHydraulic   WM Million BF Club Member   WM Pro Sawyer Network

It's Weird being the Same Age as Old People

Never allow your "need" to make money to exceed your "desire" to provide quality service.....The Magicman

tburch

It's looking great!!   

Is your property such that where the mill will be (permanently) you don't have to worry about curious eyes from passer-by's?   
Peterson 10" WPF with slabber. Cooks AC36 Diesel.
'94 Ford 4830 Diesel 2WD & FEL.  Norse 450 skid winch.  Logrite fetching arch.  Fransgard Forestry Grapple.

stanwelch

Great looking shed.

It is much nicer milling under cover for the operator AND the equipment.  8)
Woodworker, Woodmizer LT15, Stihl 026, MS261CM and 460 chainsaws, John Deere 5410 Tractor 540 Loader,Forks & Grapple, Econoline 6 ton tilt bed trailer

Ohio_Bill

Nice Job and your tractor looks like a very handy piece of equipment for the mill .
Bill
USAF Veteran  C141 Loadmaster
LT 40 HDD42-RA   , Allis Chalmers I 500 Forklift , Allis Chalmers 840 Loader , International 4300 , Zetor 6245 Tractor – Loader ,Bob Cat 763 , Riehl Steel Edger

ncsawyer

Quote from: tburch on October 09, 2015, 11:23:34 AM
It's looking great!!   

Is your property such that where the mill will be (permanently) you don't have to worry about curious eyes from passer-by's?

The mill is about 100 yards from the road and if you are looking you can see the mill from the road, but its a very rural farm community.  Usually there are just a handful of cars that pass by my house all day long. 
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

Quote from: stanwelch on October 09, 2015, 07:40:24 PM
Great looking shed.

It is much nicer milling under cover for the operator AND the equipment.  8)

Thanks!  I have followed your shed build thread and I am extremely impressed with your mill shed.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

It rained me out today, but I managed to get all of the trusses set yesterday and cut about half of my sheeting boards.  The sheeting boards will have to wait until Monday to be put on.  My metal arrives Wednesday, but I probably won't have time to get it put on until Saturday.   

 

Here is the latest picture of my progress.

2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

tburch

What is your span and how did you arrive at your truss layout?
Peterson 10" WPF with slabber. Cooks AC36 Diesel.
'94 Ford 4830 Diesel 2WD & FEL.  Norse 450 skid winch.  Logrite fetching arch.  Fransgard Forestry Grapple.

larrydown60

Shed is looking great. Do you have to have your lumber graded?

ncsawyer

Quote from: tburch on October 10, 2015, 09:46:51 PM
What is your span and how did you arrive at your truss layout?

The trusses clear span 20ft with about 2ft of overhang.   

 

This is the only picture I have of them on the computer right now.  There are actually 4 trusses in that stack.  The top cord and the vertical piece in the center are 2x6 and the bottom cord is made of 2-1x6's, one on each side of the truss.  Then there are four short 1x6's at the peak (two on each side of the truss) to hold the top cords together at the peak.  I didn't really have any plans and don't know that I have ever seen any trusses built that way, but I built some just like that for another smaller building and they worked really well. I just started building and that's what I ended up with.  If the span had been longer than 20ft, I would probably had to design a little differently. 

The roof pitch is 4/12 by the way.  Down here with no snow, some folks go as flat as 2/12.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

Quote from: larrydown60 on October 10, 2015, 10:20:05 PM
Shed is looking great. Do you have to have your lumber graded?

In cases where a building permit is required, then yes, the building inspector will require graded lumber.  However, agricultural purpose buildings do not require a building permit in our county.  Even large commercial hog and poultry operations don't require a building permit around here.  I suppose someone could argue that my mill shed is not an agricultural building, but it also doubles as my tractor shed too. ;D

If I were building a carport or garage then I would be required to get a building permit.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

stanwelch

Looks like an ag building to me! 
Bet you can fill that tree line with sawdust milling with your LT40- nice machine
Woodworker, Woodmizer LT15, Stihl 026, MS261CM and 460 chainsaws, John Deere 5410 Tractor 540 Loader,Forks & Grapple, Econoline 6 ton tilt bed trailer

ncsawyer

 

 

All the sheeting boards went up today...metal is supposed to be here this week!  I am in the short rows now!  8)  I need to add a couple of braces from each post up to the truss that is sitting on top of that post.  That should eliminate the little bit of sway from side to side.  I also plan on milling some 3/4 by 12 poplar for board and batten siding to close in the two end trusses. 

Can't wait to see some orange paint under shelter!
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

Here are the last few pictures of the mill shed.  I got it all framed up and had to wait on metal.


 

Now I finally got some orange paint under the new shelter!!  No more worrying around with that old huge heavy tarp I used to use to keep the mill out of weather. 



 



 

The new shelter should see its first sawdust on Saturday.  Have a guy brining a 42" by 8' red oak.  That one should be fun!
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

larrydown60

Fantastic job, been waiting to see the progress. Looking forward to seeing whats next Enjoy

Ljohnsaw

Quote from: ncsawyer on October 10, 2015, 10:28:54 PM
Quote from: tburch on October 10, 2015, 09:46:51 PM
What is your span and how did you arrive at your truss layout?

The trusses clear span 20ft with about 2ft of overhang.   

 

This is the only picture I have of them on the computer right now.  There are actually 4 trusses in that stack.  The top cord and the vertical piece in the center are 2x6 and the bottom cord is made of 2-1x6's, one on each side of the truss.  Then there are four short 1x6's at the peak (two on each side of the truss) to hold the top cords together at the peak.  I didn't really have any plans and don't know that I have ever seen any trusses built that way, but I built some just like that for another smaller building and they worked really well. I just started building and that's what I ended up with.  If the span had been longer than 20ft, I would probably had to design a little differently. 

The roof pitch is 4/12 by the way.  Down here with no snow, some folks go as flat as 2/12.
When I built my wife's horse barn 24 years ago, I had a 16' clear span isle-way and 18" overhang.  I made my trusses the same layout but from 2x4s (single layer) and 1/2" CDX plywood gussets for all the joints.  I didn't think 1x boards would hold up to the stress (splitting) - plus I glued all the plywood joints.  Those things were indestructible!  (no snow load)
John Sawicky

Just North-East of Sacramento...

SkyTrak 9038, Ford 545D FEL, Davis Little Monster backhoe, Case 16+4 Trencher, Home Built 42" capacity/36" cut Bandmill up to 54' long - using it all to build a timber frame cabin.

WDH

The mill looks good under there.
Woodmizer LT40HDD35, John Deere 2155, Kubota M5-111, Kubota L2501, Nyle L53 Dehumidification Kiln, and a passion for all things with leafs, twigs, and bark.  hamsleyhardwood.com

rasman57

Be proud of your effort on that nice shed.  Nothing quite like building it yourself and getting good functional use out of it.  Good work!

DeerMeadowFarm


Kipper

Looks Excellent !! I am very envious...  What was the total size of it?
LT40HD, Cat Diesel
New Holland L783
Kubota BX23
Metavic 1400XL
2016 Dodge 3500
2007 Dodge 3500 (Dump)
Belsaw 802 Edger
Too many trailers to count and all Stihl Saws!!

ncsawyer

Quote from: Kipper on October 22, 2015, 10:32:50 AM
Looks Excellent !! I am very envious...  What was the total size of it?

It is 20x48 with about 1.5 ft of overhang on all 4 sides.  That gives a few more feet under roof.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

fishfighter

Nice, just about the size I need, but I need it higher up. 13'+ to be able to park my backhoe under. ;D

Kipper

How do you plane to get the sawdust up from the backside of the mill?
LT40HD, Cat Diesel
New Holland L783
Kubota BX23
Metavic 1400XL
2016 Dodge 3500
2007 Dodge 3500 (Dump)
Belsaw 802 Edger
Too many trailers to count and all Stihl Saws!!

samandothers

WOW! Love it. ya done good... or did well! :D

ncsawyer

Quote from: Kipper on October 22, 2015, 03:07:14 PM
How do you plane to get the sawdust up from the backside of the mill?

I have a shavings bucket for the tractor that I usually use to clean up all my sawdust where ever my mill is.  I think I may board up that back wall just behind the mill to catch the saw dust.  That will give me something to push the sawdust against with the loader to make it easier to get up.  Most of my milling is not done on my site.  Most of my jobs are mobile, so I usually don't have to worry about cleaning up too much sawdust. 


 
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

I haven't been on the forum regularly for a while.  We moved to the western part of NC a little over a year ago and we sold our place in Eastern NC with the mill shed I built that is outlined in this thread.  

I have finally gotten caught up enough, that I have started on a new mill shed.  The new one will be an almost identical design, just bigger.  The new one will be 32x72.  We have gotten the posts set and have acquired enough pine to frame everything.  I will still have a 24 foot opening at the mill.  I have a 10 inch I beam to span that opening.  

I plan to get pictures of the progress as I go.  Here's what we have so far.

The last picture is my log pile.  Hopefully I have enough to get it dried in



 

 

 

2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

caveman

That is a good looking whack of pine to saw and I am surprised you could have such a flat spot in western NC.  I look forward to seeing your progress.
Caveman

thecfarm

Model 6020-20hp Manual Thomas bandsaw,TC40A 4wd 40 hp New Holland tractor, 450 Norse Winch, Heatmor 400 OWB,YCC 1978-79

ncsawyer

Quote from: caveman on November 18, 2019, 08:01:51 PM
That is a good looking whack of pine to saw and I am surprised you could have such a flat spot in western NC.  I look forward to seeing your progress.
We are in the foothills.  The problem with that particular flat spot is water.  That is where all the water from the higher areas flows.  We had to move quite a bit of dirt to build up a good building pad.  We had to bring the low side up about 2.5 feet to get it nice and level.  

Quote from: thecfarm on November 19, 2019, 06:08:59 AM
Bigger is better!!
That's always been my opinion!!
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

This is a long awaited update.  I am finally putting the finishing touches on my mill shed after starting it in 2019.  We milled everything except the posts and we made our own trusses.  The building is 32x72 with posts 12ft on center with a 24ft opening (skipped post) right in front of mill.  I am going to leave open on three sides.  All there is left to do are the batts on the siding on the long side of the barn and pull power over to it.  Between my 9-5 job, farming and adding to the family, I didn't think, I'd ever get there, but finally did!




 

 

 

 

 

 

 

 

 

 

 

 



2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

beenthere

Very nice. Congrats for getting it this far along. 
south central Wisconsin
It may be that my sole purpose in life is simply to serve as a warning to others

Resonator

Like the half-wood, half-tin wall idea, easy to fix or modify down the road. smiley_thumbsup
Under bark there's boards and beams, somewhere in between.
Cuttin' while its green, through a steady sawdust stream.
I'm chasing the sawdust dream.

Proud owner of a Wood-Mizer 2017 LT28G19

Andries

I thought the first version was looking pretty darn good.
But this second version of your sawmill barn is looking even better, well done!
Question: when you built your trusses, is the bottom cord 1x or 2x material? Construction screws or air nailer? 
Perfect photo sequence, shows the build from start to finish.
I'd say you're getting to be pretty darn good at this building thing. 👍
LT40G25
Ford 545D loader
Stihl chainsaws

ncsawyer

Quote from: Andries on January 30, 2023, 11:43:47 AMQuestion: when you built your trusses, is the bottom cord 1x or 2x material? Construction screws or air nailer?

The bottom cord is made from 1x6s. On one side of the truss the 1x6s are joined in the middle of the truss.  On the opposite side they are joined about halfway between the middle and end with a 2x6 block, so everything wouldn't be joined in the same place.  I used an air nailer with ring shank nails.  Here's another view of a truss that might help.

 
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

ncsawyer

Quote from: Resonator on January 30, 2023, 11:38:26 AM
Like the half-wood, half-tin wall idea, easy to fix or modify down the road. smiley_thumbsup
Thanks! Using metal at the bottom should prevent rot and deterioration from water splashing back on the building from the drip line of the roof.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

barbender

Nice, nice, nice!! I am in envy! I like the metal at the bottom, and your trusses are out of the box. Did you design them yourself, or see them somewhere else first?
Too many irons in the fire

Bruno of NH

Lt 40 wide with 38hp gas and command controls , F350 4x4 dump and lot of contracting tools

fluidpowerpro

Change is hard....
Especially when a jar full of it falls off the top shelf and hits your head!

ncsawyer

Quote from: barbender on January 30, 2023, 01:01:03 PM
Nice, nice, nice!! I am in envy! I like the metal at the bottom, and your trusses are out of the box. Did you design them yourself, or see them somewhere else first?
I guess you could say that I designed them myself.  I built a platform and attached to the back of my gooseneck trailer so I would have a large enough flat area to build them. I had a picture in my mind and built one and it turned out good, so I screwed down blocks and made a jig and made duplicates of my first one.
2015 Wood-Mizer LT40DD35
Woodmaster 718 planer
Ford 445 Skip Loader

BoomerMT

WOW, that is a super impressive shed....Nice work

scsmith42

That really came out well!  I need to hop on the bike one weekend and stop by to say "Howdy" and check out your operation.

Sweet job on the trusses too.

Scott
Peterson 10" WPF with 65' of track
Smith - Gallagher dedicated slabber
Tom's 3638D Baker band mill
and a mix of log handling heavy equipment.

jpassardi

Looking good - no small amount of work/time to get that done part time with little to no help. I know that drill...
LT15 W/Trailer, Log Turner, Power Feed & up/down
CAT 416 Backhoe W/ Self Built Hydraulic Thumb and Forks
Husky 372XP, 550XPG, 60, 50,   WM CBN Sharpener & Setter
40K # Excavator, Bobcat 763, Kubota RTV 900
Orlan Wood Gasification Boiler -Slab Disposer

Thank You Sponsors!