iDRY Vacuum Kilns

Sponsors:

Concrete floor revisited

Started by wbrent, May 26, 2024, 07:04:58 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

wbrent

Planning to put in a concrete pad for my mill this summer. Unless you guys talk me out of it. Mill sits under the lean to off my garage right now. Stable ground with 3/4 minus crushed rock. Lean to is 12x36. undecided on whether i need concrete to fill the whole space or just enough to cover the mill. Leaning towards filling most of the space. I guess cost will dictate that. Im in atlantic Canada. Is there options for concrete these days? HAve i heard of concrete with fiberglass in it or something? Does that negate putting rebar or steel mesh in it?
What thickness do i need? Im a hobby guy so not doing any production milling. But my mill can tske a 29" diameter log up to 16 feet. I still anticipate putting cross sleepers on top of the pad and then tieing them together. Mainly to bring mill to a height im comfortable with and to stabilize the mill from moving. So wondering if its worthwhile embedding some thredded rod in the concrete in the areas where the cross sleepers will go. Or is it just as easy to bolt them down after the fact?
CAn you offer advice on other prep work and tips before i get into this? Thanks in advance

tule peak timber

We poured a 6 inch slab with a lot of steel in it and drilled for bolts later. The slab has held an LT 35, an Lt 70 , and now holds an Lt 15. You will find opinions vary as to making the mill hard and fast. WOC
persistence personified - never let up , never let down

Sod saw

.


Our saw is siting on  slab that is between 6 and 8 inches thick.  That slab is sitting on 2 inches of foam board and that board is sitting on 6 inches of pea stone (for drainage).

There is 1/2 inch diameter rod in the slab and I requested fibers to also be mixed in the cement when delivered.  The mix is 4000 PSI.

Why so much?  Our saw has a bed extension requiring the slab to be about 40 feet long.   We also have 4 feet of freezing depth in the ground.  I also am cutting oak etc. that is over three feet diameter and over 20 feet long.  sometimes they land hard when they fall on that slab and I prefer not to have to replace it.

The saw is not bolted down to that slab.  When those logs roll on to the mill they bang into the backstops and the mill frame will scoootch over slightly.  To prevent that movement across the slab I drilled oversized holes and epoxied 5/8 inch diameter rod into the slab where the feet are located.  Those solid rods prevent the saw from scoootching across the slab.  Plan on installing more than one rod at every leg (foot).  Not bolting the mill frame down to the slab prevents it from bending out of shape as those larger logs roll.  The mill frame will just settle back down where it was before the log rolled.  A little give and take is not a bad thing.

That's the way we did here.  I suspect that others have found different solutions.

I am delighted with the cement as it is easier to clean up and more comfortable to walk on.


.
LT 40 hyd.          Solar Kiln.          Misc necessary toys.
.
It's extremely easy to make things complicated, but very difficult to keep things simple.
.

doc henderson

I use steel rebar, when possible, at least along the edges, with heavy matt 8 x 20 feet all across.  I like the fiber reinforced for thin stuff, like the floor over plywood with pex for heat in my shop floor, over I trusses.  Only cracks are where 4 inch would have cracked also, like a narrow dog leg section.  I also added it to the 1.5 inch shallow end floors and slope walls and floor of the deep end of our pool.  no cracks when we change the liner.
Timber king 2000, 277c track loader, PJ 32 foot gooseneck, 1976 F700 state dump truck, JD 850 tractor.  2007 Chevy 3500HD dually, home built log splitter 18 horse 28 gpm with 5 inch cylinder and 32 inch split range with conveyor powered by a 12 volt tarp motor

scsmith42

I think that more of an issue is slab thickness where you are loading logs.  You're dealing with the weight of the loader as well as the log.  

We've had logs weighing up to 4 tons on the Baker, plus the 4.5 ton weight of the baker.  But that pales compared with the 19 ton weight of the articulating loader.

So I'd study if/where your loader will be rolling onto the slab, and make sure your perimeter footers are strong and that there is no organic material in your sub-base (and that it's very well compacted).
Peterson 10" WPF with 65' of track
Smith - Gallagher dedicated slabber
Tom's 3638D Baker band mill
and a mix of log handling heavy equipment.

wbrent

Thanks guys. Glad i asked. HAd no idea people were making these so thick. I was thinking more like 4" thickness. Might have to re think this. The loader will never get its wheels on the pad. So at least dont have to worry about the weight of the tractor. Love to hear others thoughts.

doc henderson

I think a steel reinforced 4-inch pad will be fine.  a well compacted base so the settling is minimum.  I like the idea of a wood plank under the jack to absorb some of the forces and spread out the impact over more sq. footage.
Timber king 2000, 277c track loader, PJ 32 foot gooseneck, 1976 F700 state dump truck, JD 850 tractor.  2007 Chevy 3500HD dually, home built log splitter 18 horse 28 gpm with 5 inch cylinder and 32 inch split range with conveyor powered by a 12 volt tarp motor

NewYankeeSawmill

When I worked in the print-biz I watched a press or two get installed. They would form up and pour 2 parallel rectangular supports for the press to set on. Maybe 2' tall x 2' wide x long-as-the-press... This provided clearance underneath the press for various maintenance tasks in addition to a stable base. The form was over 2 feet deep into the ground (e.g. 4+ ft of concrete)... those presses had to be stable to run right. I was looking at doing something similar when considering a stationery mill. I figured it would make handling the sawdust easier and make it a good working height for me (I'm 6'4", nothing is built to my size).
I ended up buying my mill w/ the trailer package in-part b/c a local old-timer recommended it to get the mill at a good working-height; and he was right! Prior to that decision I looked at stationary mills and pouring a pad vs the press-column idea and it was a huge cost savings on the volume of concrete. Almost $10k IIRC... Run some numbers on the back of an envelope or get a local contractor to quote something.
Norwood LUMBERPRO HD36V2

SawyerTed

Thickness and rebar are important but compression psi of the concrete is equally so.  

Ask your concrete contractor about higher compression ratings - 6,000 pound or 8,000 pound concrete.  Unless specified most concrete for slabs is 4,000 pound concrete here.  
Woodmizer LT50, WM BMS 250, WM BMT 250, Kubota MX5100, IH McCormick Farmall 140, Husqvarna 372XP, Husqvarna 455 Rancher

barbender

 Concrete is expensive enough now that it may make sense to engineer your pad with thicker areas for where you know increased loads will be. If you have a definite layout, there's no reason you couldn't increase the thickness to whatever is required just beneath the mill feet, and log deck supports. 

 For instance, in our basement I poured a 4" floor, but doubled the thickness under a post that is supporting loads all the way down from the ridge beam of the house. 

 The downside to this is that it looks you into one layout if you wanted to change anything down the line.
Too many irons in the fire

doc henderson

I did the same in the basement of the shop.  ran a 12 inch deep 2-foot wide beam down the center under the floor, for a wall in the basement to support the I truss', that are now supporting tools that are at 2K pounds.
Timber king 2000, 277c track loader, PJ 32 foot gooseneck, 1976 F700 state dump truck, JD 850 tractor.  2007 Chevy 3500HD dually, home built log splitter 18 horse 28 gpm with 5 inch cylinder and 32 inch split range with conveyor powered by a 12 volt tarp motor

YellowHammer

I love my slab, WM recommended 6" thick, rebar on 24" and I thickened it on the edge, basically a footing, when the loader or forklift might get on it.  

YellowHammerisms:

Take steps to save steps.

If it won't roll, its not a log; it's still a tree.  Sawmills cut logs, not trees.

Kiln drying wood: When the cookies are burned, they're burned, and you can't fix them.

Sawing is fun for the first couple million boards.

Be smarter than the sawdust

Thank You Sponsors!